Before starting pergola assembly, check that the delivered shipment matches the approved order. Count the packages, record their condition and reconcile the labelled parts with the packing list. Finding a missing bracket or an incorrect beam after installation has begun makes the issue harder to document and resolve.
This pergola delivery inspection checklist is for distributors, contractors and project buyers receiving an aluminium pergola. It is a receiving check, not a structural assessment or an installation guide. Use the documents supplied for the exact model and order; configurations differ across aluminium pergola systems.

Prepare the order documents before the shipment arrives
Keep one current document set available to the person receiving the goods. It should include the order reference, approved drawing revision, agreed finish and options, packing list, assembly instructions and the contact responsible for delivery questions. Mark any unconfirmed item as open rather than assuming it is included.
If the order has changed since quotation, use the latest agreed version. A roof motor, side screen or lighting component shown in an early proposal may not be included in the final order. For future projects, use the pergola OEM quotation checklist to establish this record before ordering.
1. Record package count and condition before unpacking
Compare the number and identifiers of the packages with the shipment documents. Record the delivery date and note any package that is visibly crushed, torn, wet or open. Take an overall photograph of the shipment and separate close-ups of each affected package, including its label.
Keep receiving checks separate from unloading work. Use the unloading arrangements and equipment specified for the shipment, handled by suitably qualified personnel. Do not open or move an unstable package simply to complete a photograph. Confirm how delivery exceptions should be recorded with the responsible supplier or carrier contact; do not assume one reporting process applies to every shipment.
2. Reconcile the parts with the packing list
Unpack in the sequence allowed by the supplied instructions and retain the connection between each package label and its contents. Count by part identifier, not just by appearance. Similar-looking profiles or brackets can serve different positions in the approved layout.
| Component group | What to compare | What to record |
|---|---|---|
| Posts and beams | Part identifiers, quantities and specified dimensions against the approved drawing | Package label, part label and any mismatch |
| Louvers or other roof components | The roof type and component quantities listed for this order | Count and visible condition, without forcing components to fit |
| Brackets, fasteners and covers | Kit codes and quantities against the supplied parts list | Missing kits, unlabelled bags or damaged items |
| Drainage components | Only the gutters, outlets, covers or other pieces specified for this configuration | Listed items received and any unresolved identification |
| Optional equipment | Ordered screens, motors, controls or lighting against the final option list | Model labels and missing or different items; do not power up for an informal test |
This table is a checking framework, not a promise that every pergola shipment contains these components. The order-specific packing list determines what should be present.
3. Document visible damage without altering the part
Under suitable light, look for visible dents, bent edges, damaged finishes and broken fittings. Photograph both the complete part and the affected area, keeping its identifier in the record. Note whether the observation was made before or after unpacking.
Keep affected parts separate and identifiable while the supplier reviews the issue. Do not drill, cut, straighten, repaint or substitute a questionable part to keep assembly moving. Such changes alter the evidence and may introduce a different fit or safety problem. This receiving check does not establish whether concealed damage is present.
4. Match labels to the approved layout before assembly
Ask the installation team to confirm the drawing revision, component orientation and any position-specific labels before work begins. Where a dimension needs checking, compare it with the approved drawing and the measurement method in the supplied instructions, not a generic size found online.
A complete delivery does not prove that foundations, wall connections, electrical provisions or site dimensions are suitable. Those checks remain separate and should be addressed by the responsible professionals using the project documents. This checklist does not establish wind or snow performance, local approval or compliance.
5. Send one clear discrepancy record
A useful report connects each observation to a specific package and part. Avoid sending a group of unidentified close-ups or describing several issues in one sentence. Use a separate row for every missing, incorrect or damaged item.
- Order and drawing reference: identify the agreed configuration and revision.
- Package and part identifier: copy the labels exactly as shown.
- Expected and received quantity: distinguish a shortage from a part that cannot yet be identified.
- Observed issue: describe what is visible without guessing its cause.
- Photographs: include the overall package, label, whole part and relevant detail.
- Requested clarification: state what the installation team needs resolved before using that component.
Follow the reporting route and timing in the agreed delivery documents. The checklist does not set a universal replacement policy, warranty outcome or claim deadline.
6. Close the receiving check before handing over to installers
Keep unresolved items on an open-issue list. Record the supplier’s response and the responsible installation team’s decision before affected components are used. Do not interpret an acknowledgement of a report as approval to assemble a damaged or unidentified part.
Hand over the checked packing list, approved drawings, photographs and any written clarifications together. For repeat orders, discuss part labelling and document quality when comparing pergola suppliers. These details make the next receiving check easier to carry out consistently.